How do we recognize a risk early enough to act?

Missing risk triggers

Define observable signals and the decision they should trigger. A useful trigger is linked to a response window, not merely a condition noticed after the impact has occurred.

What to do now

  1. Identify early warning signals
  2. Set a practical observation method
  3. Agree the action threshold and owner
  4. Test whether enough response time remains
Recommended action flow for missing risk triggers: Identify early warning signals then Set a practical observation method then Agree the action threshold and owner then Test whether enough response time remains. Escalate when the warning arrives too late for the planned response.

When to escalate

Escalate when

The warning arrives too late for the planned response.

Who decides

The accountable risk owner

Example

A supplier's missed design checkpoint triggers review before the final delivery date becomes unrecoverable.

Mistake to avoid

Using project failed as the trigger for contingency.

Prevent a repeat

Review whether response tasks and trigger conditions remain appropriate as the project changes.

Suggested ApprovedFlow setup

  • Documents
  • Tasks
  • Approvals

Store the risk assessment as a controlled project document and assign response tasks; do not assume a native risk engine is enabled. See the platform