Our schedule ignores holidays and part-time staff. How do we correct it?

Invalid working calendars

Rebuild dates using actual working calendars and availability. A mathematically linked schedule is still wrong when its calendars assume people are available when they are not.

What to do now

  1. Collect relevant working calendars
  2. Record leave and part-time availability
  3. Recalculate affected task dates
  4. Confirm revised commitments with owners
Recommended action flow for invalid working calendars: Collect relevant working calendars then Record leave and part-time availability then Recalculate affected task dates then Confirm revised commitments with owners. Escalate when the corrected calendar causes a material milestone breach.

When to escalate

Escalate when

The corrected calendar causes a material milestone breach.

Who decides

The project manager and relevant commitment owner

Example

A ten-day task assigned to a half-time specialist spans approximately four working weeks before other constraints.

Mistake to avoid

Counting calendar days as working days without agreement.

Prevent a repeat

Compare forecast versus actual results for comparable tasks, separating effort, elapsed time, waiting and scope change.