Every task is on time, but the project is late. What are we missing?

Missing schedule relationships

Individual task dates can look healthy while handoffs, integration, and dependencies push the finish date. Reconstruct the end-to-end delivery path rather than judging progress from isolated tasks.

What to do now

  1. Trace the final deliverable backward
  2. Add missing handoffs and approvals
  3. Check dependency logic and calendars
  4. Recalculate the completion forecast
Recommended action flow for missing schedule relationships: Trace the final deliverable backward then Add missing handoffs and approvals then Check dependency logic and calendars then Recalculate the completion forecast. Escalate when the integrated forecast exceeds the agreed delivery tolerance.

When to escalate

Escalate when

The integrated forecast exceeds the agreed delivery tolerance.

Who decides

The project manager and relevant commitment owner

Example

Development finishes on Friday, but integration cannot start until a shared environment is available the following week.

Mistake to avoid

Averaging task status colors to determine the project finish date.

Prevent a repeat

Compare forecast versus actual results for comparable tasks, separating effort, elapsed time, waiting and scope change.