I estimated two days, but the task took five. Why did I underestimate it?

Possible planning fallacy

This can reflect planning fallacy: relying on an optimistic internal story rather than comparable actual results. One overrun alone does not prove bias, so also check scope changes, waiting time, and interruptions.

What to do now

  1. Define what done included
  2. Compare similar tasks and their actual durations
  3. Separate effort from waiting and rework
  4. Use a justified range for the next estimate
Recommended action flow for possible planning fallacy: Define what done included then Compare similar tasks and their actual durations then Separate effort from waiting and rework then Use a justified range for the next estimate. Escalate when repeated underestimation threatens a committed milestone.

When to escalate

Escalate when

Repeated underestimation threatens a committed milestone.

Who decides

The project manager and relevant commitment owner

Example

A two-day build took five elapsed days because review waited two days and a defect required another day.

Mistake to avoid

Multiplying every estimate by an arbitrary factor without checking causes.

Prevent a repeat

Compare forecast versus actual results for comparable tasks, separating effort, elapsed time, waiting and scope change.

Suggested ApprovedFlow setup

  • Tasks
  • Timesheets
  • Resources

Keep planned dates and assumptions with the affected task, compare recorded actuals, and attach the revised forecast for review. See the platform

Related cases

Practice references