My team confuses effort with duration. How should we estimate?

Effort-duration confusion

Effort measures work input; elapsed duration also includes availability, sequencing, and waiting. Estimate both explicitly rather than assuming that eight hours of effort always fits into one calendar day.

What to do now

  1. Estimate focused work hours
  2. Check the assignee's actual availability
  3. Add required waits and dependencies
  4. Record effort and forecast dates separately
Recommended action flow for effort-duration confusion: Estimate focused work hours then Check the assignee's actual availability then Add required waits and dependencies then Record effort and forecast dates separately. Escalate when a commitment relies on people working more hours than available.

When to escalate

Escalate when

A commitment relies on people working more hours than available.

Who decides

The project manager and relevant commitment owner

Example

An eight-hour review takes four working days when the reviewer has two available hours each day.

Mistake to avoid

Dividing effort by headcount without checking parallel work.

Prevent a repeat

Compare forecast versus actual results for comparable tasks, separating effort, elapsed time, waiting and scope change.