The project is spending faster than planned. What should I check first?

Unexplained cost variance

Compare spending with the work actually accomplished and the timing of commitments. Early spending can be legitimate, but it needs explanation before concluding that the project is over budget.

What to do now

  1. Reconcile actual and committed costs
  2. Compare them with achieved work
  3. Identify timing differences and genuine overruns
  4. Update the forecast to complete
Recommended action flow for unexplained cost variance: Reconcile actual and committed costs then Compare them with achieved work then Identify timing differences and genuine overruns then Update the forecast to complete. Escalate when the forecast exceeds authorized funding or cash availability.

When to escalate

Escalate when

The forecast exceeds authorized funding or cash availability.

Who decides

The budget owner and authorized finance representative

Example

An early equipment purchase explains some spending, while repeated rework explains a genuine forecast increase.

Mistake to avoid

Judging performance from expenditure alone.

Prevent a repeat

Review remaining cost and commitments, not only money already spent; reconcile with the authorized finance source.