We keep changing the baseline to hide variance. How should rebaselining work?

Baseline manipulation

Preserve the original commitment and change history while approving a new baseline only for a justified reason. A new baseline should improve control, not erase evidence of prior performance.

What to do now

  1. Confirm the reason for rebaselining
  2. Assess remaining scope and forecasts
  3. Obtain the required authorization
  4. Retain comparisons with prior baselines
Recommended action flow for baseline manipulation: Confirm the reason for rebaselining then Assess remaining scope and forecasts then Obtain the required authorization then Retain comparisons with prior baselines. Escalate when rebaselining is proposed mainly to conceal poor performance.

When to escalate

Escalate when

Rebaselining is proposed mainly to conceal poor performance.

Who decides

The sponsor or formally delegated governance body

Example

A major approved scope reduction creates a new baseline while reports retain the original delivery comparison.

Mistake to avoid

Resetting every late task to today and calling the project on track.

Prevent a repeat

Review overdue decisions and confirm that decision makers have the authority and evidence they need.