Our dependency dates keep changing. How do we protect the project?

Volatile external readiness

Track the supplying team's evidence-based forecast and assess the effect of each change. Develop feasible alternatives where possible and escalate when the dependency cannot support the required outcome.

What to do now

  1. Validate the current readiness evidence
  2. Model downstream effects
  3. Identify alternative sequencing or supply
  4. Obtain a decision on the remaining exposure
Recommended action flow for volatile external readiness: Validate the current readiness evidence then Model downstream effects then Identify alternative sequencing or supply then Obtain a decision on the remaining exposure. Escalate when repeated changes remove credible recovery options.

When to escalate

Escalate when

Repeated changes remove credible recovery options.

Who decides

The accountable integration or dependency owner

Example

A team advances independent preparation while escalating an unstable environment delivery date.

Mistake to avoid

Moving your own milestone repeatedly without explaining the cause and decision.

Prevent a repeat

Verify dependency completion with the consuming team and test the integrated outcome early enough to act.