How do we know a technical project is ready for handover?

Incomplete technical transition

Verify that the receiving team can operate, monitor, support, and recover the delivered service with appropriate access and evidence. A document handover alone does not demonstrate operational capability.

What to do now

  1. Confirm operating responsibilities
  2. Test key support and recovery procedures
  3. Transfer controlled configuration and documentation
  4. Obtain explicit readiness acceptance
Recommended action flow for incomplete technical transition: Confirm operating responsibilities then Test key support and recovery procedures then Transfer controlled configuration and documentation then Obtain explicit readiness acceptance. Escalate when the receiving team cannot safely sustain the service.

When to escalate

Escalate when

The receiving team cannot safely sustain the service.

Who decides

The technical owner and authorized release decision maker

Example

Operations demonstrates a recovery task and finds the relevant runbook before accepting responsibility.

Mistake to avoid

Declaring handover complete when a folder of files is sent.

Prevent a repeat

Review real execution evidence and maintainability alongside feature completion; do not treat an unrun test as passed.