Users keep asking for small extras. How do I prevent scope creep?

Accumulating unapproved scope

Small requests become a large commitment when their combined impact is invisible. Capture each request, compare it with the agreed scope, and obtain a deliberate trade-off decision before implementation.

What to do now

  1. Record the requested addition
  2. Check the agreed scope boundary
  3. Estimate its cumulative delivery impact
  4. Approve, exchange, defer, or reject the request
Recommended action flow for accumulating unapproved scope: Record the requested addition then Check the agreed scope boundary then Estimate its cumulative delivery impact then Approve, exchange, defer, or reject the request. Escalate when the combined additions threaten an agreed constraint.

When to escalate

Escalate when

The combined additions threaten an agreed constraint.

Who decides

The scope owner and authorized sponsor

Example

Five half-day additions consume several days, so the sponsor exchanges them for a lower-priority report.

Mistake to avoid

Absorbing every small request to avoid an awkward conversation.

Prevent a repeat

Review ambiguous requirements and unresolved acceptance conditions before the affected work begins.

Suggested ApprovedFlow setup

  • Projects
  • Tasks
  • Documents
  • Approvals

Keep the agreed scope and acceptance evidence with the project; record any proposed change and its decision separately. See the platform