We are under budget but behind schedule. Is that good news?

Misleading underspend

Underspend may reflect work not yet performed rather than efficiency. Compare the remaining work and future commitments with the budget before claiming savings.

What to do now

  1. Confirm completed scope
  2. Identify deferred work and costs
  3. Estimate remaining effort and commitments
  4. Report cost and schedule together
Recommended action flow for misleading underspend: Confirm completed scope then Identify deferred work and costs then Estimate remaining effort and commitments then Report cost and schedule together. Escalate when delayed work creates a forecast funding or deadline breach.

When to escalate

Escalate when

Delayed work creates a forecast funding or deadline breach.

Who decides

The budget owner and authorized finance representative

Example

A team has spent less because testing has not begun, not because testing will cost less.

Mistake to avoid

Calling unspent money a saving while the work remains unfinished.

Prevent a repeat

Review remaining cost and commitments, not only money already spent; reconcile with the authorized finance source.