We inherited a project with no charter. Can we continue?

Missing project mandate

Keep essential reversible work moving while reconstructing the mandate. Do not assume that old meeting notes authorize spending, scope, or decisions that nobody has accepted.

What to do now

  1. Inventory existing commitments
  2. Identify the sponsor and decision rights
  3. Draft a concise charter from current evidence
  4. Ratify scope and authority before major commitments
Recommended action flow for missing project mandate: Inventory existing commitments then Identify the sponsor and decision rights then Draft a concise charter from current evidence then Ratify scope and authority before major commitments. Escalate when current commitments exceed confirmed funding or authority.

When to escalate

Escalate when

Current commitments exceed confirmed funding or authority.

Who decides

The accountable sponsor

Example

A replacement project manager records an interim mandate and obtains confirmation before signing the next supplier milestone.

Mistake to avoid

Backdating approval documents to make the record appear complete.

Prevent a repeat

At each stage decision, check that the expected outcome, owner and justification remain valid.