The vendor says the delay is our fault. How do we establish facts?

Disputed delay responsibility

Build a shared timeline of required inputs, actual submissions, decisions, and dependencies. Keep recovery moving while authorized commercial staff assess responsibility and contractual consequences.

What to do now

  1. Collect dated evidence from both sides
  2. Map the dependency sequence
  3. Separate disputed facts from agreed facts
  4. Agree recovery actions and commercial review
Recommended action flow for disputed delay responsibility: Collect dated evidence from both sides then Map the dependency sequence then Separate disputed facts from agreed facts then Agree recovery actions and commercial review. Escalate when the dispute affects material payments, remedies, or obligations.

When to escalate

Escalate when

The dispute affects material payments, remedies, or obligations.

Who decides

The authorized procurement or commercial owner

Example

The parties compare when access was requested, provided, and actually usable.

Mistake to avoid

Arguing responsibility from memory while delivery remains blocked.

Prevent a repeat

Compare supplier evidence with agreed obligations; refer contract interpretation and remedies to qualified owners.

Suggested ApprovedFlow setup

  • Vendors
  • Documents
  • Tasks
  • Approvals

Keep supplier commitments and evidence linked to the project, assign follow-up work, and route commercial decisions to authorized owners. See the platform