How do we define a dependency so it can be managed?

Vague dependency record

Describe the needed output, supplying owner, receiving work, required date, and readiness evidence. A department name or general statement is not enough to coordinate delivery.

What to do now

  1. Name the specific required input
  2. Identify supplying and receiving owners
  3. Agree date and acceptance evidence
  4. Track forecast changes and impact
Recommended action flow for vague dependency record: Name the specific required input then Identify supplying and receiving owners then Agree date and acceptance evidence then Track forecast changes and impact. Escalate when the supplier has not accepted a critical required commitment.

When to escalate

Escalate when

The supplier has not accepted a critical required commitment.

Who decides

The accountable integration or dependency owner

Example

The dependency states that a tested service account must be available before integration testing begins.

Mistake to avoid

Writing depends on IT without specifying what IT must provide.

Prevent a repeat

Verify dependency completion with the consuming team and test the integrated outcome early enough to act.